Project: Lewis Court Cottages EWI Project
Client: Aberdeen City Council
Value: £342k
Award Date: August 2015
Completion Date: February 2016
Aberdeen City Council awarded Skyform the contract to undertake a 16 week project which consisted of the EWI, re-roofing and re-rendering of 15 no properties, 7 in Phase 1 and 8 in Phase 2.
However due to variations issued on behalf of the client both phases shall require increased cover to the roofing as when initially stripped the sarking and fibreboard was of poor quality.
Additional works have been instructed and are currently underway with an extension of time being granted to cover the changes to the fully boarded alternative roofing specification.
Skyform’s in house labour have carried out the works under the supervision of Site Manager Pat Doherty and the contract was managed by Paul Miller.